Whitianga: Smooth Commissioning on the Coromandel

How early planning and strong collaboration made Lodestone's Whitianga solar farm one of the smoothest commissioning projects MMDMM has delivered.

12/4/2025

Lodestone Energy opened its fourth solar farm, Pāmu Rā ki Whitianga, in December 2025 on the outskirts of Whitianga township on the Coromandel Peninsula. The region's first utility scale solar farm began generating just in time for the summer influx of holidaymakers, and it moved Lodestone closer to its vision of a solar farm in every community.

Now fully operational, the farm generates approximately 49 GWh of certified renewable electricity each year, enough to power around 6,800 homes. It features 53,400 solar panels and 7,150 pilings, and under Lodestone's agrivoltaics dual use model, sheep graze under and around the panels so that energy generation and traditional farming operate side by side. Construction began in late 2024 and created local jobs during the 12 month build. The project also includes the planting of 9,300 eco sourced natives, along with the restoration of a wetland area.

Generation peaks over summer, which suits a region where electricity demand triples over the Christmas and New Year period. Powerco, the local electricity network operator, completed commissioning of a new switching station that connects the solar farm to the Coromandel network. The station is designed for a future 66kV to 110kV conversion as demand grows, and it strengthens security of supply for the upper Coromandel Peninsula.

Mansoor Shah, founder and CEO of MMDMM, represented MMDMM on the project as a contractor, and says Whitianga was one of the smoothest sites the team has ever worked on. The difference came down to preparation. Unlike earlier projects, the team had plenty of time before work began, which allowed them to build a full commissioning schedule as part of the initial scope, and to test the commissioning plans properly before going to site.

The team was also well resourced. Shein, a full time SCADA specialist from Lodestone, joined the project and is now the main SCADA lead there. Mansoor worked alongside him, and the two collaborated closely to bring everything together. Julian Lampen, a graduate engineer, also joined the effort, which meant the team could run around the site and complete all of the necessary testing. According to Mansoor, the group worked really well together.

The results showed in the delivery. Field equipment performed well, the main SCADA system went up smoothly, and ICCP connectivity came through with very little difficulty. Everything kicked off quickly, with one exception.

The exception was the connection to Powerco's network. Although it used the same architecture as the Horizons connection, the links did not perform as well, and communication with Powerco's network proved harder than expected. Mansoor and the team put in considerably more effort to work through and resolve the problems. Even so, the rest of the project went to plan, and the team's early planning and strong collaboration kept the commissioning on track.

Pāmu Rā ki Whitianga was the fourth farm Lodestone delivered in partnership with Infratec and New Energy, with installation efficiencies doubling since the first project. At the time of its opening, Lodestone was constructing its fifth site in South Canterbury, with a sixth in Central Hawke's Bay due to begin in 2026, and expected to have brought 230 GWh of new renewable energy to market by the end of 2025, enough to power 32,000 Kiwi homes annually.